As rapidly as Saudi Crown Prince MBS unveiled one extraordinary project after another in the $1.5 trillion Neom city, from Sindalah and Trojena to The Line and beyond, news of scaling back and now outright cancellations has followed just as quickly. The decision to move the 10th Asian Winter Games in 2029 from the unfinished, Blade Runner-style Trojena resort to Almaty in Kazakhstan was, in hindsight, a clue in disguise. It now seems the crown prince will have to recalibrate his vision yet again, as the $38 billion Trojena project, billed as the region’s first outdoor ski resort, appears unlikely to materialize in its original form.

Neom has terminated Webuild’s contract covering the three dams meant to create the freshwater lake, along with the architectural structure known as The Bow. An important nuance here is that, in Webuild’s own words, this was a termination for convenience, which suggests a client-led decision rather than any public accusation of contractor failure. That is not the only blow. The list of terminations also includes Eversendai’s structural steel contract for the Ski Village. With no ski village, no lake, and no Asian Winter Games to host, this geography-defying statement of Saudi Arabian ambition now appears to be unraveling, leaving skiing in the desert looking more like a distant fantasy than an imminent reality.

What makes the retreat especially striking is how much had already been built. Trojena was conceived as a 60-square-kilometer mountain destination within Neom, rising to elevations of up to 2,600 meters. The original vision included a year-round mountain resort, an artificial freshwater lake, the Ski Village, The Bow hotel component, The Vault vertical village concept, ultra-luxury residences, and a hospitality lineup that stretched from Raffles and W to JW Marriott and Ritz-Carlton Reserve.

The canceled Webuild contract, reportedly worth about $5 billion, was central to the creation of a lake roughly 2.8 kilometers long, fed by a system of dams. And that was only one part of the undertaking. According to The Wall Street Journal, Trojena executives shared in 2024 that the project required 130,000 tons of steel, roughly double the amount used in the Empire State Building.

With the Webuild package said to be about 30 percent complete when the termination came through, the company is expected to be reimbursed for site disengagement and demobilization. That makes the collapse all the more jarring. Trojena had been under development for years and, unlike some other Neom ideas, was already visibly taking shape. It rose alongside the seahorse-shaped superyacht island Sindalah, which launched in 2024, and at one stage looked like one of the more advanced parts of the megaproject. The Line may have been scaled down, and perhaps something similar once seemed possible for Trojena.

Instead, giant steel structures meant to hold hotels, along with a dramatic network of elevated ski runs, had already started taking shape in the Ski Village area before the project was thrown into limbo. The site that was once meant to host the 2029 Asian Winter Games now appears headed for an indefinite reset, with partially built works left suspended in the mountains. In addition to Trojena, Neom has also canceled contracts tied to tunnel sections of The Line in northwest Saudi Arabia.